12 x 12 patio, 4 x 8 pavers, running bond
- Area
- 144.0 sq ft
- Pavers
- 636 at 4.20 per sq ft, 5% waste
- Base
- 1.78 yd³ · 2.5 tons at 4"
- Sand
- 0.6 tons bedding · 4 joint bags
- Edge
- 48 ft
JoyOne factory · hardscape takeoff
Measure the patio once. This page turns that area into pavers with the joint in the count, the base in cubic yards and tons, the bedding sand, the joint sand and the length of edge restraint — and draws the section the numbers describe.
636 pavers · 1.78 yd³ base · 4 joint bags
144.0 sq ft · Running bond (stretcher, half offset)
144.0 sq ft (13.4 m²) · 12.0 x 12.0 ft · Running bond (stretcher, half offset)
| Line | Quantity | Amount |
|---|---|---|
| Pavers | 636 pavers | $540.60 |
| Gravel base | 2.5 tons | $136.89 |
| Bedding sand | 0.6 tons | $27.00 |
| Polymeric joint sand | 4 bags | $128.00 |
| Edge restraint | 48 ft | $216.00 |
| Materials | $1,048.49 | |
| Labour and excavation | 144.0 sq ft | $2,304.00 |
| Total | $23.28 per sq ft | $3,352.49 |
Prices are examples you can edit. Base and sand tonnage use the densities in the form; the bag counts use 0.5 cu ft bags unless your product says otherwise.
Every number below comes from the same engine that runs in the browser, at build time, so the examples cannot drift from the calculator above.
Almost no patio is one rectangle. A typical back garden is a main terrace, a path along the wall and a small landing at the step, and the three are rarely the same width. Measure each one to the outside face of the edge restraint — the pavers sit inside the restraint, so the restraint line is the area the base has to cover, not the paver line.
The form takes a rectangle, a circle, an L-shape or an area you have already measured, and it adds them. A circle is worth measuring as a diameter rather than guessing: a 10 ft circle is 78.5 sq ft, and a 12 ft circle is 113 sq ft, so two feet of diameter is 45% more paving. For an L-shape, type the overall rectangle and the notch cut out of one corner; a notch removed from a corner takes as much edge as it adds, so the perimeter — and therefore the edge restraint — is the same as the overall rectangle.
If you have a plan drawing, check one dimension on the ground before you trust the rest. Plans are drawn to the property line and patios are built to the downpipe, and the difference is usually a few inches in the wrong direction. Inches do not change the tonnage much; they do change whether the last course is a full paver or a 2 in sliver.
Pavers are counted over the joint, not over the paver. A 4 x 8 in paver with a 3/16 in joint occupies 4.1875 x 8.1875 in of surface, which is 34.29 sq in, so a square foot holds 144 / 34.29 = 4.20 pavers. The same paver with a 1/8 in joint is 4.30 per square foot and with a 1/4 in joint 4.11 — a swing of about 4.5% across the joint range, which on a 400 sq ft patio is twenty pavers.
The joint width is set by the paver, not by preference. A chamfered or tumbled paver needs a wider joint to look right and to take sand; a tight, dimensional paver looks wrong with a 1/4 in gap. The three common values are 1/8, 3/16 and 1/4 in, and 3/16 in is the usual default for a 60 mm paver.
The same pitch drives the joint sand. Each paver owns one length plus one width of joint centreline, so a 4 x 8 paver owns 12 in of joint and a 12 x 12 paver owns 24 in — but there are far fewer of them per square foot. The sand page does that arithmetic from the same numbers, which is why the two answers cannot disagree.
The allowance you add is not a cushion for bad measuring; it is the material the pattern eats at the edges. Running bond needs half-pavers at the end of alternate courses, so 5% covers the cuts on a rectangular patio. A 45-degree herringbone needs a cut on almost every edge paver and turns the corners into triangles, which is why this site defaults it to 10% and 90-degree herringbone to 12%.
Basket weave needs a true 2:1 paver to close, and it defaults to 7% because the perimeter still gets cut. Stack bond is the cheapest pattern to lay and the least forgiving: joints line up in both directions, so any size variation in the pallet shows as a wandering line, and it still needs 5% for the ends.
Two things add to the allowance and neither is in the default. A diagonal layout on a patio with many corners wastes more than the same layout on a plain rectangle, and a job where the pavers are cut on site with a disc cutter wastes more than one cut on a wet saw. If your patio has four inside corners, add a few percent and accept that the spare pallet is cheaper than a second delivery.
What the paver count depends on
A paver is a wear surface sitting on a bedding layer sitting on a compacted base. ICPI’s construction bulletin puts the bedding sand at 1 in uncompacted, screeded to a constant thickness, and the base at 4 in compacted for sidewalks, patios and pedestrian areas over well-drained soil, 6 in for a residential driveway. The base is the layer that carries the load; the sand is there to bed the pavers, not to make up for a base that is 1/2 in low at one end.
The base goes down in lifts of 4 to 6 in with a plate compactor in the 5,000 to 7,000 lbf class, and each lift is compacted before the next. ICPI targets 98% of standard Proctor density. That is a specification a contractor can test; on a domestic job the practical version is several passes with a heavy plate, in thin layers, with the surface checked against a straightedge.
The edge restraint is the part that is easiest to skip and hardest to fix. ICPI asks for at least 1 in of vertical face in contact with the side of the paver, and it goes in before the bedding sand so the sand can be screeded to the top of the restraint. Without it the pavement spreads at the perimeter, the joints open, and the pattern that was tight in April is loose by August.
It will not tell you whether your soil drains, whether the ground freezes, or whether the patio needs a geotextile separator. It will not size a driveway for a delivery truck, and it will not tell you that a 1.5% slope is enough where your garden already falls towards the house. Those are site decisions, and the honest answer is that the person who can see the site decides them.
It also will not quote a price. The unit prices in the form are examples so the arithmetic is visible, and the page labels them as examples. A paver that costs $0.85 in one yard costs $1.40 in another, and a ton of crushed stone is a local product with a local price; three quotes beat any national average, including one this site could invent.
What it does do is make the takeoff checkable. Every number on the page can be recomputed from the four inputs beside it, the section drawing is drawn from the same depths, and the printable list carries the assumptions with the quantities so the person at the counter can see what was ordered and why. If a number looks wrong, the arithmetic is on the page to argue with.
It depends on the paver and the joint. A 4 x 8 in paver with a 3/16 in joint gives 4.20 per sq ft, so a 144 sq ft patio is 605 pavers before waste and 636 with a 5% allowance; the same paver with a 1/8 in joint gives 4.30, and with a 1/4 in joint 4.11. A 12 x 12 in paver with a 3/16 in joint gives 0.97 per sq ft, because the joint is a much larger share of a big unit.
Five percent for running bond or stack bond on a simple rectangle, 7% for basket weave, 10% for 45-degree herringbone and 12% for 90-degree herringbone. Those are trade rules of thumb rather than a standard, and they go up on a patio with many corners or a layout cut on site. The form lets you type any allowance you prefer.
Add the layers: paver thickness, 1 in of bedding sand and the compacted base — 4 in (100 mm) for a patio or walkway, 6 in (150 mm) for a residential driveway — plus the fall if the surface slopes. A 2 3/8 in paver on a 4 in patio base is 7 3/8 in of build-up, and the excavation has to be that deep plus the thickness of the edge restraint.
Not on a patio that will stay flat. The sand is a 1 in bedding layer, not a base: ICPI puts a compacted aggregate base under it, 4 in for pedestrian areas and 6 in for driveways. Sand alone moves, pumps and settles, and the joints open as it does.
Yes. ICPI requires an edge restraint with at least 1 in of vertical face against the paver, installed before the bedding sand is screeded. Without it the perimeter spreads under load, joints widen and the bond that holds the pattern together stops working.
| Value | As used here | Basis | Source |
|---|---|---|---|
| Bedding sand thickness | 1 in (25 mm) uncompacted | Screeded to a constant nominal thickness; the sand is not there to fix an uneven base. | CMHA / ICPI PAV-TEC-002 — Construction of Interlocking Concrete Pavements |
| Bedding sand specification | ASTM C33 or CSA A23.1 FA1, ≤1% passing No. 200 | Washed concrete sand; masonry sand, limestone screenings and stone dust are explicitly excluded. | CMHA / ICPI PAV-TEC-017 — Bedding Sand Selection for Interlocking Concrete Pavements |
| Base depth, pedestrian | 4 in (100 mm) compacted | Sidewalks, patios and pedestrian areas over well-drained soil; thicker for weak, wet or freezing ground. | CMHA / ICPI PAV-TEC-002 — Construction of Interlocking Concrete Pavements |
| Base depth, residential driveway | 6 in (150 mm) compacted | Same bulletin for cars and light trucks; the CMHA base article repeats it and adds 50% per poor site condition. | CMHA — Proper Concrete Paver Base and Depth |
| Base depth, residential street | 8 in (200 mm) compacted | Parking lots and residential streets; industrial pavements are designed, not tabulated. | CMHA — Proper Concrete Paver Base and Depth |
| Minimum surface slope | 1.5% (about 3/16 in per ft) | ICPI states 1.5% minimum, and 1% longitudinal / 2% cross-slope for roads; this site defaults to 2%. | CMHA / ICPI PAV-TEC-002 — Construction of Interlocking Concrete Pavements |
| Joint sand material | ASTM C144 mason sand or polymeric sand | ICPI allows ASTM C33 concrete sand too, but notes it is harder to sweep into the joints. | CMHA / ICPI PAV-FAQ-002 — Installing Standard Interlocking Concrete Pavers |
| Polymeric sand depth | joint filled to 1/8 in (3 mm) below the top | Manufacturer instruction; on a repair the old sand comes out at least 1.5 in deep. | Alliance Gator — polymeric jointing material FAQ |
| Joint sand stabilizer threshold | recommended above 7% slope | ICPI names high-slope applications as one of the cases where stabilizer is worth it; optional otherwise. | CMHA / ICPI PAV-TEC-005 — Cleaning, Sealing and Joint Sand Stabilization |
| Base compaction | 4–6 in lifts, 98% standard Proctor | ICPI: 7,000 lbf reversible plate for 4–6 in lifts, thinner lifts for a 5,000 lbf machine; ASTM D698 density. | CMHA / ICPI PAV-TEC-002 — Construction of Interlocking Concrete Pavements |
| Bagged sand sold by volume | 0.5 cu ft per bag | The retail hardscape sands are sold in 0.5 cu ft bags and priced by depth; a 1 cu ft bag is a different product. | QUIKRETE quantity calculators — hardscape sands |
| Aggregate and sand tonnage | tons = cubic yards × density | Editable in the form. 1.40 short tons per cu yd for crushed base and 1.35 for sand are typical supplier figures, not a spec — ask your yard. | CMHA — Proper Concrete Paver Base and Depth |
| Paver thickness by use | 2 3/8 in pedestrian, 3 1/8 in streets | 60 mm and 80 mm units; both are editable because makers sell 2 3/4 in and 3 1/8 in variants. | CMHA / ICPI PAV-TEC-002 — Construction of Interlocking Concrete Pavements |
| Edge restraint | at least 1 in of vertical face on the paver | ICPI minimum restraining surface; more for heavy-duty applications. | CMHA / ICPI PAV-TEC-002 — Construction of Interlocking Concrete Pavements |
This is an estimating tool. The product label, the paver manufacturer’s installation guide and your local building department decide the detail on your site — the numbers here are a starting point, and every price is an example you are expected to change.