144 sq ft patio at the 4 in minimum
- Volume
- 1.78 yd³ (48.0 cu ft)
- Weight
- 2.5 tons at 1.40 ton/yd³
- Bags
- 96 at 0.50 cu ft
JoyOne factory · hardscape takeoff
Pick what the pavement is for and the base depth follows from the published minimums. The answer is the volume to order, the tonnage at your supplier’s density, and the number of lifts to compact.
1.78 yd³ · 2.5 tons · 96 bags
144.0 sq ft · Running bond (stretcher, half offset)
144.0 sq ft (13.4 m²) · 12.0 x 12.0 ft · Patio or courtyard (pedestrian)
| Input | Value used | Why |
|---|---|---|
| Use | Patio or courtyard (pedestrian) | 4 in is the published minimum for it |
| Site allowance | 0% | CMHA: +50% per poor condition (soil, drainage, frost) |
| Density | 1.40 ton/yd³ | Your supplier’s figure; 1.40 is a typical crushed stone value |
| Bag size | 0.50 cu ft | Retail aggregate bags are usually 0.5 cu ft |
| Waste | not included | Order a little over for spillage and a thicker low corner |
Subgrade is graded and compacted before the base goes down, and the base is not used to fill a dip. The tonnage excludes waste and any allowance for a thicker edge.
Every number below comes from the same engine that runs in the browser, at build time, so the examples cannot drift from the calculator above.
ICPI’s construction bulletin gives three minimums for a compacted aggregate base: 4 in (100 mm) for sidewalks, patios and pedestrian areas over well-drained soil, 6 in (150 mm) for residential driveways, and 8 in (200 mm) for parking lots and residential streets. Those are minimums under good conditions, and the bulletin says so: colder climates, wet soils and weak soils all need more.
The association’s own guidance on poor sites is unusually concrete: add 50% to the minimum for each of three conditions that does not apply — good drainage, good soil and a mild climate. A driveway where none of the three holds starts at 6 in and becomes 15 in. That is not a rule of thumb dressed up as code; it is a planning allowance, and it is why the form has an extra-depth field rather than a single number.
The other thing that changes depth is what the base is for. A base under a pedestrian patio carries foot traffic and furniture. A base under a driveway carries a car’s wheel loads, which arrive at a point and repeat, and that is a different problem: it is why the same stone is 50% thicker for the driveway and why a hot tub or a delivery truck is an engineered question rather than a table lookup.
The usual material is a dense-graded aggregate — the “3/4 in minus” or “crushed stone base” sold at a quarry, with a gradation that includes fines so it compacts into a tight, stable layer. CMHA points at ASTM D2940 as the grading requirement to ask the quarry about. It is a local product: the stone under a patio in one state is not the stone in another, and the name on the ticket matters less than the gradation.
An open-graded aggregate — clean stone with the fines washed out — is the material for permeable pavements. ICPI is explicit that it is not the recommendation for a standard sand-set paver on a vehicular application, and that a patio built over it should expect to top up the joint sand from time to time. If your reason for an open-graded base is drainage, the whole assembly has to be designed for drainage, not just the bottom layer.
What the base is not: sand, and not a thin scatter of stone to level a hollow. Sand does not compact into a load-spreading layer, and a base that varies in thickness because it was used to fill a dip will settle where it is thickest. The subgrade is graded and compacted first, the base goes on top of that at a consistent thickness, and the bedding sand is 1 in everywhere.
The base is spread in lifts of 4 to 6 in (100 to 150 mm) and each lift is compacted before the next goes down. ICPI names a 7,000 lbf reversible plate compactor for those lifts and says thinner lifts are needed with a 5,000 lbf machine. A small single-direction plate is not the same tool: it will move the surface and leave the bottom of the lift loose.
The density target is 98% of standard Proctor (ASTM D698), with modified Proctor (ASTM D1557) preferred where vehicles run. On a domestic job you will not see a density gauge, so the practical proxy is discipline: thin lifts, several passes, moisture in the stone — damp, not wet — and a check with a straightedge after each lift. Where the base meets an edge restraint or a wall, compact along the edge rather than only in the middle, because that is where the plate is hardest to get.
The calculator returns a lift count so the tonnage can be ordered in stages. On a 300 sq ft driveway at 6 in the base is 5.6 cu yd, and one lift would be a mistake: three 2 in lifts with a plate between them is the same stone, compacted properly, and it is the difference between a base and a pile.
What changes the tonnage
The arithmetic is simple and the unit is where people go wrong. Area in square feet times depth in inches divided by 12 is cubic feet; divide by 27 for cubic yards; multiply by short tons per cubic yard for the tonnage. A cubic yard is 27 cubic feet, so a 300 sq ft patio at 4 in is 100 cu ft, 3.70 cu yd, and at 1.40 tons per cubic yard that is 5.2 tons.
That density of 1.40 is a typical figure for crushed stone base, not a specification, and it varies with the rock and with how wet the pile is. Limestone, granite and trap rock do not weigh the same; a yard that has been rained on weighs more than one that has not, and you pay for the water. Ask the supplier for tons per cubic yard and type their number into the form — it is the single biggest lever on the tonnage after the depth.
Bagged base is a different product at a different price: 0.5 cu ft per bag is the retail unit, so a 100 cu ft base is 200 bags. That is fine for a step or a small landing and absurd for a driveway, which is why the answer is given in all three units and the yard is usually the right one.
The base is the layer the edge restraint is fixed into — spikes, a concrete curb or a plastic edge — and it goes in before the bedding sand so the sand can be screeded to the top of the restraint. ICPI asks for at least 1 in of vertical face against the paver. It also matters that the restraint is continuous: a gap of a foot at a gate post is where the pavement starts to spread.
Drainage is set at the subgrade, not at the pavers. ICPI states a minimum slope of 1.5%, with 1% longitudinal and 2% cross-slope for roads. The base follows that fall, the bedding sand follows the base, and the pavers follow the sand. Trying to build the fall into the bedding layer alone gives a base that is thicker at one end and a patio that holds water at the other.
Finally, the base is not finished until it is protected. A completed base left open to a rainy week, walked on by everyone on site, is a base that needs re-compacting before the sand goes down. If the pavers are not going on the same day, keep the last lift 1/2 in high and finish it when the bedding sand is ready.
At the 4 in pedestrian minimum it is 48 cu ft, which is 1.78 cu yd. At 1.40 tons per cubic yard that is 2.5 tons, or 96 bags of 0.5 cu ft. If the ground is wet or weak, add the planning allowance before ordering.
Six inches compacted for a residential driveway over well-drained soil, per ICPI. Parking areas and residential streets go to 8 in. Weak, wet or freezing ground needs more — the association suggests adding 50% to the minimum for each of those conditions that applies.
You can, and it is common: building a patio to the driveway depth costs more stone and buys margin. What you should not do is build a driveway to the patio depth, because the base is what spreads the wheel load and 4 in under a car is not the same pavement as 4 in under a table.
About 1.4 short tons per cubic yard for a typical crushed stone base, but it is a supplier figure rather than a constant: the rock type, the gradation and the moisture all move it. Ask your yard for tons per yard and put that number in the form.
A geotextile separator between a fine subgrade and the base keeps the two from mixing, and ICPI treats it as optional depending on the soil. On clay or silt it is cheap insurance; on clean granular subgrade it adds little. The base depth does not change either way.
| Value | As used here | Basis | Source |
|---|---|---|---|
| Bedding sand thickness | 1 in (25 mm) uncompacted | Screeded to a constant nominal thickness; the sand is not there to fix an uneven base. | CMHA / ICPI PAV-TEC-002 — Construction of Interlocking Concrete Pavements |
| Bedding sand specification | ASTM C33 or CSA A23.1 FA1, ≤1% passing No. 200 | Washed concrete sand; masonry sand, limestone screenings and stone dust are explicitly excluded. | CMHA / ICPI PAV-TEC-017 — Bedding Sand Selection for Interlocking Concrete Pavements |
| Base depth, pedestrian | 4 in (100 mm) compacted | Sidewalks, patios and pedestrian areas over well-drained soil; thicker for weak, wet or freezing ground. | CMHA / ICPI PAV-TEC-002 — Construction of Interlocking Concrete Pavements |
| Base depth, residential driveway | 6 in (150 mm) compacted | Same bulletin for cars and light trucks; the CMHA base article repeats it and adds 50% per poor site condition. | CMHA — Proper Concrete Paver Base and Depth |
| Base depth, residential street | 8 in (200 mm) compacted | Parking lots and residential streets; industrial pavements are designed, not tabulated. | CMHA — Proper Concrete Paver Base and Depth |
| Minimum surface slope | 1.5% (about 3/16 in per ft) | ICPI states 1.5% minimum, and 1% longitudinal / 2% cross-slope for roads; this site defaults to 2%. | CMHA / ICPI PAV-TEC-002 — Construction of Interlocking Concrete Pavements |
| Joint sand material | ASTM C144 mason sand or polymeric sand | ICPI allows ASTM C33 concrete sand too, but notes it is harder to sweep into the joints. | CMHA / ICPI PAV-FAQ-002 — Installing Standard Interlocking Concrete Pavers |
| Polymeric sand depth | joint filled to 1/8 in (3 mm) below the top | Manufacturer instruction; on a repair the old sand comes out at least 1.5 in deep. | Alliance Gator — polymeric jointing material FAQ |
| Joint sand stabilizer threshold | recommended above 7% slope | ICPI names high-slope applications as one of the cases where stabilizer is worth it; optional otherwise. | CMHA / ICPI PAV-TEC-005 — Cleaning, Sealing and Joint Sand Stabilization |
| Base compaction | 4–6 in lifts, 98% standard Proctor | ICPI: 7,000 lbf reversible plate for 4–6 in lifts, thinner lifts for a 5,000 lbf machine; ASTM D698 density. | CMHA / ICPI PAV-TEC-002 — Construction of Interlocking Concrete Pavements |
| Bagged sand sold by volume | 0.5 cu ft per bag | The retail hardscape sands are sold in 0.5 cu ft bags and priced by depth; a 1 cu ft bag is a different product. | QUIKRETE quantity calculators — hardscape sands |
| Aggregate and sand tonnage | tons = cubic yards × density | Editable in the form. 1.40 short tons per cu yd for crushed base and 1.35 for sand are typical supplier figures, not a spec — ask your yard. | CMHA — Proper Concrete Paver Base and Depth |
| Paver thickness by use | 2 3/8 in pedestrian, 3 1/8 in streets | 60 mm and 80 mm units; both are editable because makers sell 2 3/4 in and 3 1/8 in variants. | CMHA / ICPI PAV-TEC-002 — Construction of Interlocking Concrete Pavements |
| Edge restraint | at least 1 in of vertical face on the paver | ICPI minimum restraining surface; more for heavy-duty applications. | CMHA / ICPI PAV-TEC-002 — Construction of Interlocking Concrete Pavements |
This is an estimating tool. The product label, the paver manufacturer’s installation guide and your local building department decide the detail on your site — the numbers here are a starting point, and every price is an example you are expected to change.